Colchester 18 MW fuel-cell site

A 17-acre Connecticut site with an 18 MW on-site generation facility permitted for Bloom fuel cells, offered on a $1 a year ground lease with power sold from $0.15/kWh.

Colchester, Connecticut

Observed

View official listingCompare nearby optionsRequest site information

Location Published city or county and state.
Colchester, Connecticut 1
State US state containing the property.
Connecticut 1
Grid operator Grid operator (ISO/RTO) when the source names it.
Not published
Marketing party Developer or brokerage publishing this opportunity; not necessarily the owner.
Baxtel listing (owner confidential) 1
Offering Advertised or reported transaction. Developer inquiry means the project page invites enquiries without sale or lease terms. Under contract and Sold rows are reported transactions, kept as price and power comparables.
Sale or lease 1
Published status Status on the marketing page. Availability of land does not establish availability of power.
Listed (updated Oct 3, 2026) 1
Land acres Advertised gross acreage, including undevelopable areas unless the acreage note says otherwise.
17 1
Acreage basis Scope, approximation or usable-area qualification attached to the published acreage.
Not published
Stated capacity MW Published headline capacity, with its basis in the adjacent column. This is not a normalized IT-load or energized-power measure.
18 1
Power basis What the stated MW represents: design, utility study, agreement, generation or existing supply. All are attributed claims.
Permitted on-site natural gas fuel cells; power sold under a PPA from $0.15/kWh 1
Utility Electric utility explicitly named by the source. A nearby transmission line does not establish a service agreement.
Not published
Power timing Published energization target or relative delivery claim, preserved as written rather than converted into a new date.
Not published
Zoning / entitlement Published zoning or approval status; verify the applicable parcel and permitted use with the authority.
Not published
Infrastructure Published transmission, substation, water or fiber details.
40,000 sq ft data center pad; multiple fiber providers 1
Asking price $ Published total asking price in US dollars. Empty means no public numeric asking price was verified.
Not published

Other Eastern US opportunities