Brazoria County site (CleanSpark)
CleanSpark agreed to buy 447 acres with a long-term transmission facilities extension agreement for a 300 MW demand load, expandable to 600 MW.
Observed
Read the deal reportCompare nearby optionsRequest site information
Parcel file
Field definitions- Location Published city or county and state.
- Brazoria County, Texas 1
- State US state containing the property.
- Texas 1
- Grid operator Grid operator (ISO/RTO) when the source names it.
- Not published
- Marketing party Developer or brokerage publishing this opportunity; not necessarily the owner.
- CleanSpark, buyer 1
- Offering Advertised or reported transaction. Developer inquiry means the project page invites enquiries without sale or lease terms. Under contract and Sold rows are reported transactions, kept as price and power comparables.
- Under contract 1
- Published status Status on the marketing page. Availability of land does not establish availability of power.
- Acquisition agreed; closing expected Q1 2026 1
- Land acres Advertised gross acreage, including undevelopable areas unless the acreage note says otherwise.
- 447 1
- Acreage basis Scope, approximation or usable-area qualification attached to the published acreage.
- Not published
- Stated capacity MW Published headline capacity, with its basis in the adjacent column. This is not a normalized IT-load or energized-power measure.
- 300 1
- Power basis What the stated MW represents: design, utility study, agreement, generation or existing supply. All are attributed claims.
- Transmission facilities extension agreement for 300 MW demand load; potential 600 MW 1
- Utility Electric utility explicitly named by the source. A nearby transmission line does not establish a service agreement.
- Not published
- Power timing Published energization target or relative delivery claim, preserved as written rather than converted into a new date.
- Not published
- Zoning / entitlement Published zoning or approval status; verify the applicable parcel and permitted use with the authority.
- Not published
- Infrastructure Published transmission, substation, water or fiber details.
- Transmission-level power 1
- Asking price $ Published total asking price in US dollars. Empty means no public numeric asking price was verified.
- Not published